Pre enabling works for the new DART

In August 2017 Ryebridge were contracted to clear the route for the new DART (Direct Airport Rail Transfer) contractor.

The project was predominantly airside and includes perimeter track diversion, de-icing tank relocation, a new snow fleet area, fuel tank relocation, bus parking, airside fence realignment, taxiway realignment, service clearance.

This project is due to be completed by the end of 2017.