£8.2m Hotel Taxiway, Stand 16 and South Stands

Project Works and Key Quantities

  • Excavation

  • 18500m3 Material recycled and re-used within the works

  • 4500m3 Supply and compaction of Type 1

  • 12500m3 Cement Bound Granular Material

  • 15,700T Foam Base

  • 4800T Asphalt Surfacing

  • 19500m2 Asphalt reinforcement grid

  • 14200m2 PQ Concrete

  • 2200m3 Drainage

  • 4000m Attenuation Tanks

  • 1750m3 AGL Pit and Ducting System

  • 7000m and 104 Pits Complete on time and under budget

Complete on time and under budget

Project Principals and Objectives

The project was to construct a new taxiway in order to enable growth in passenger numbers and flights using the airport. In addition, to extend an existing aircraft stand at either end to accommodate 2 additional aircraft. The third area of works was to reconfigure an existing executive aircraft stands to accommodate additional aircraft and new roadway for aircraft maintenance vehicles and plant.

For more information click on the image below.