£80M Tottenham Hotspur Football Club

Project Details

Original contract Site clearance and removal of hazardous material. Principal contractor Management Subcontractors. Bulk dig and hazardous material removal Sheet piling Concrete piles Pile caps Service diversion Infrastructure drainage design and construction Demolition

Project Principals and Objectives

In July 2014 Ryebridge was originally contracted by THFC to undertake a 12 week project valued at £500k with a brief to reduce the existing level of the new stadium site by 1m. By June 2016 the level of Ryebridge’s involvement in the overall project had increased to in excess of £12m as Ryebridge was appointed Principal Contractor.

For more information click on the image below.

THFC jpeg new.JPG