£12M Tottenham Hotspur Football Club

In June 2014 Ryebridge Construction was appointed principle contractor to Tottenham Hotspur Football Club (THFC), leading on a two-year project to prepare the site for its new multi-million -pound stadium. Ryebridge was tasked with overseeing the safe running of the project on behalf of the football club.

As principal contractor Ryebridge was responsible for providing health, safety and welfare for up to 250 workers. Initial enabling works such as welfare compound set up, site security, pedestrian and site traffic logistics.

THFC final pdf with pix embedded_Page_01.jpg
THFC final pdf with pix embedded_Page_01.jpg
THFC final pdf with pix embedded_Page_02.jpg

As the project got up to speed Ryebridge supervised and managed THFC subcontractors through the bulk dig, removal of hazardous and non-hazardous material from the site, demolition of adjacent buildings, sheet pile installation, groundwater pumping setup, CFA piling and pile cap construction. Following this period of work in Tottenham Ryebridge have built strong relationships with the sub - contractors that have helped construct the foundations of the new stadium.

These include SE Davis, Fussey Piling, Cementation Skanska, WJ Groundwater, Wingate Electrical and AJ Morrisroe.

THFC final pdf with pix embedded_Page_02.jpg
THFC final pdf with pix embedded_Page_03.jpg
THFC final pdf with pix embedded_Page_04.jpg
THFC final pdf with pix embedded_Page_03.jpg
THFC final pdf with pix embedded_Page_05.jpg
THFC final pdf with pix embedded_Page_04.jpg

The carbon savings of this project were staggering.  All the hard standings on site were crushed and then reused on site to form haul roads and set down points. All the inert material that was not suitable to be washed was formed into a noise reducing bund along the edge of the M25.

THFC final pdf with pix embedded_Page_05.jpg

The washable inert material (ballast) was washed and screened into four different stockpiles. Sand, 10mm shingle, 20mm shingle, 40mm shingle and silt. The 40mm shingle was then crushed and screened once more. The only waste product was the silt.

THFC final pdf with pix embedded_Page_06.jpg

Weekly progress meetings were held in the stadium board room and Ryebridge played an important part in assisting THFC surveyors with progress reports and sub-contractor progress on site. The site was registered with the Considerate Contractors Scheme (CCS) and received a good report when inspected by the CCS representative. A daily report was compiled by the Ryebridge site manager and sent to Ryebridge senior management and THFC project team. The advanced stadium works managed by Ryebridge won a gold award at the 2016 Rospa Awards at the Excel, London.

THFC final pdf with pix embedded_Page_06.jpg

Working closely with Haringey Council’s highways authority Ryebridge installed storm drainage outfalls across the main high road into the Moselle culvert and excavated numerous trial holes in the footpaths and roads around the stadium for existing services identification to assist the design team.

THFC final pdf with pix embedded_Page_07.jpg
THFC final pdf with pix embedded_Page_07.jpg

As THFC were still using the existing stadium for home football matches Ryebridge ensured that the works on site did not interfere with the day by day operations of the stadium and worked closely with the stadium management and security teams. During the closed season Ryebridge managed to ensure critical works were completed and the area around the stadium reinstated before the football season commenced.

THFC final pdf with pix embedded_Page_08.jpg
THFC final pdf with pix embedded_Page_08.jpg

 

High profile buildings adjacent to the new stadium site were demolished by Ryebridge and our help with the initial enabling works helped to get the stadium project up to speed.

THFC final pdf with pix embedded_Page_09.jpg

In January 2016 Ryebridge successfully handed the running of the site to Mace and continued managing satellite sites within half a mile of the stadium which were predominantly used as a base for the ongoing washing of excavated ballast and batching of concrete from a Tarmac operated batching plant.

THFC final pdf with pix embedded_Page_10.jpg
THFC final pdf with pix embedded_Page_10.jpg